Construction technology and maintenance of SPC floor

发布者: 大巨龙  时间:2021-07-30

 

Installation of SPC floor

Floating installation method

  Do not fix it on the base layer one by one; Cut expansion joints shall be reserved at the bottom of all door posts, and heavy objects shall not be placed above the SPC floor; Skirting or transition strips shall be installed at the edges to protect exposed floor edges, but shall not be fixed through the floor.


  1. Determine the arrangement direction of the floor; It is usually laid along the length of the room; It can also be laid according to personal preferences.

  2. In order to avoid the floor near the wall and door being too narrow or too short, the number of complete floors that can be arranged and the remaining space that needs to be covered by some floor plates shall be calculated according to the width of the room. Divide the remaining space by two to calculate the width and length of part of the floor.

  3. If the width of the first row of floor does not need to be cut, the suspended tongue and tenon shall be cut off to make the edge against the wall neat.

  4. During installation, the expansion gap between walls shall be reserved. Leave space for the natural expansion and contraction of the floor. When the floor laying length exceeds 10m, it is recommended to disconnect the laying.


  5 install the floor from left to right. Place the first floor in the upper left corner of the room to expose the joint tongue groove of the head and side.

  6. When installing the second floor in the first row, insert the tongue and tenon on the short side into the tongue groove on the short side of the first floor. Continue to use the above method to install other floors along the first row.

  7. When installing the second row, cut a floor to be at least 1524cm shorter than the first floor in the first row (the rest of the last floor in the first row can be used). When installing the first floor, insert the tongue and tenon of the long side into the tongue groove of the long side of the first row of floor.

  8 when installing the second floor in the second row, insert the tongue and tenon of the short side into the tongue groove of the short side of the first floor installed in front.


  9. Align the tongue end of the floor just above the long edge of the floor.

  10. Insert the tongue and tenon of the long side into the tongue groove of the adjacent floor at an angle of 20-30 degrees by gently sliding along the short side joint. In order to make the "sliding" smooth, you can lift the floor on the left slightly.

  11. The rest of the floors in the room can be installed in the same way. Ensure that necessary expansion clearance is left between and all fixed vertical parts (such as walls, doors, cabinets, etc.).

  12. The floor can be easily cut with a cutting saw. Just scribe on the surface of the floor and then cut.

 


tel:15821396693 Address: Jin Teng Road, Jinshan District, Shanghai E-mail:dajulongfloor@126.com